Do you need a building permit to renovate in Ottawa?

Cosmetic work usually does not need a permit. Anything that changes walls, plumbing or structure usually does. Here is where the City of Ottawa draws the line.

New roof and floor framing during a GCO Contracting home build

By GCO Contracting Inc. ·

The short answer.

Under Ontario’s Building Code Act, you need a building permit to construct a new building, build an addition, or alter a building or structure over 10 square metres (about 108 square feet). The City of Ottawa publishes two lists to help: projects that need a permit and projects that do not.

Even when no permit is needed, the work still has to meet the Ontario Building Code and the Zoning By-law. If you are not sure about your project, call 3-1-1 and ask before you start.

Renovations that usually need a permit.

These come from the City’s list of building permit projects and its building permit FAQ.

  • Adding or removing walls to create different room sizes or uses
  • One- and two-storey additions
  • A new window where there was none, or enlarging or moving a window or door
  • Altering, adding or extending plumbing (replacing existing fixtures is the exception)
  • Structural repairs, foundation repairs and drain tile replacement
  • Changing how part of a building is used
  • A deck attached to the house with a walking surface more than 24 inches above grade
  • A detached garage, shed or other accessory building over 10 square metres

Renovations that usually do not.

The City lists these as not needing a building permit. The exemptions do not apply to designated heritage buildings or properties in a Heritage District Overlay.

  • Painting, decorating and landscaping
  • New flooring
  • Replacing kitchen or bathroom cabinets, as long as plumbing fixtures stay in the same place
  • Replacing doors or windows in the same size opening
  • New asphalt shingles on a roof
  • Replacing an existing hot water tank, or installing air conditioning or a heat pump
  • Damp proofing an existing basement
  • A deck less than 24 inches above grade (except at the main entrance)
  • A one-storey storage shed of 15 square metres or less, with no plumbing

Kitchens, bathrooms and basements.

A kitchen where new cabinets and counters go in on the same layout generally does not need a permit. Moving the sink, adding a plumbing line or taking out a wall to open the kitchen up does. Removing a load-bearing wall also needs engineering; see our load-bearing wall guide.

The same logic applies to bathrooms: swapping a toilet, vanity or tub in place is replacing fixtures, while moving them or adding a new bathroom alters the plumbing system.

For basements, the City’s answer is that you may need a permit: if the work includes building, extending or materially altering anything, a permit is required. In practice most full basement finishes (new walls, a bathroom, a bedroom) need one. A basement apartment changes how the space is used and has its own rules; see legal basement apartments in Ottawa.

Electrical work is separate.

The City does not regulate electrical installations, so work that is only electrical does not need a City building permit. It falls under the Electrical Safety Authority (ESA). Ontario advises hiring a licensed electrical contractor, getting the ESA/ECRA licence number on the written estimate, and confirming they will get a certificate of inspection when the work is done.

Who gets the permit?

The City says it is the owner’s responsibility to make sure a permit is obtained when required. You can authorize your contractor or designer to apply, but you should see the permit before any work starts. The owner and the contractor are equally liable under the Building Code Act.

Ontario’s consumer guidance adds one more step: if your contractor is getting the permit for you, have that written into the contract. At GCO we coordinate permits and City approvals as part of the project.

How long it takes, and what happens next.

Once the City has a complete application, it aims to review it in about five working days and tell you whether the permit will be issued. That is an estimate, not a guarantee; an incomplete application gets a deficiency letter instead.

  • Construction must seriously start within six months of the permit being issued, or it can be revoked
  • The permit has to be posted on site while the work is underway
  • Inspections happen at key stages; book them 48 hours ahead
  • Work covered up before an inspection may have to be opened again

Quick answers.

Short, plain answers. Anything else, call and ask for Aurelio, the owner of GCO Contracting.

Call 613-862-RENO

  • Usually, yes. The City of Ottawa says you may need one, and that a permit is required if the work includes building, extending or materially altering anything. A basement finish with new walls, a bathroom or a bedroom normally needs a permit. Damp proofing an existing basement does not.

  • No, as long as the plumbing fixtures stay in the same location. Moving the sink, extending plumbing or removing a wall to change the layout does need a building permit.

  • The owner. The City of Ottawa says the owner must make sure a permit is obtained when required. You can authorize your contractor to apply, but you should see the permit before work starts, and ideally have the contractor’s responsibility for it written into your contract.

  • For a complete application, the City aims to review it in about five working days and let you know whether the permit will be issued. Incomplete applications receive a deficiency letter, which adds time.